Estimates
MATERIALS REQUIREMENTS IN RESIDENTIAL BUILDINGS BASED ON PLINTH AREA BASIS
Material | Single Storey | Double Storey | Four Storey (R.C.C. Framed) |
Bricks (100 Nos.) | 2.26 A+66.8 | 2.15A+63 | 2.56A-0.0096A2-26.2 |
Cement (Tonnes) | 0.153A+0.57 | 0.145A+0.54 | 0.2024A-0.364 |
Steel (Kg) | 21.3A-314 | 21.97A- 305 | 102.46A-0.401A2-1662 |
Sand (m3) | 0.47A-7 | 0.43A-5.6 | 397A-0.38 |
Coarse aggregate (m3)
(i) 20 mm & down (ii) 40 mm & down |
0.176A-0.21
0.145A+1.5
|
0.178A-0.21
0.075A+0.78 |
0.363A-0.76
0.0027A+0.0001A2 +0.45
|
Timber (m3)
(i) Frames & shutters (ii) Shuttering |
0.019A+0.23
0.0042A |
0.019A+0.23
0.0042A |
0.02A+0.11
0.0097A-0.03 |
Lime (quintal) | 0.145A-0.35 | 0.083A-0.17 | 0.063A-0.08 |
Surkhi (m3) | 0.052A-0.37 | 0.026A-0.18 | 0.01A |
Bitumen (Kg) | 1.836A-9 | 0.918A -4 | 0.357A+0.14 |
Glass Panes(m2) | 0.047A | 0.047A | 0.047A |
Primer for oil paint (litre) | 0.048A | 0.048A | 0.045A+0.56 |
Oil Paint (litre) | 0.08A+0.27 | 0.08A+0.27 | 0.075A+0.93 |
Note:-
- The above expression is applicable for plinth area ranges from 30 to 300m2(one floor)
- In case of single and double storeyed framed buildings, and up to 100m2 (one floor) for four storeyed framed building.
- The above table gives material for one floor / storey. Multiply the No. of Storeys to get total Quantity.
Rough Estimate (m3 / m2) (Based on plinth area basis)
- Earthwork:
300 Class loading | 500 class loading | ||
Single bay |
Two bay | Single bay | Two bay |
0.1 + (22.2 nD/q) |
0.1 +( 18.9 nD/q) | 0.1 +( 24.8 nD/q) | 0.1 +( 21.5 nD/q) |
Where
n = No. of floors
D = Depth in meters
q = SBC in KN/m2
2.Brick work for foundation and basement :
Q = m3 / m2
Span | Single bay | Two bay |
4.0 m | 0.17 | 0.14 |
5.0 m | 0.16 | 0.13 |
6.0 m | 0.14 | 0.12 |
7.0 m | 0.13 | 0.11 |
3.Brick wall for superstructure:
Load bearing = 0.40 to 0.45 m3 / m2
4.DPC :
Framed structure = 0.1 m2 / m2
Load bearing = 0.23 m2 / m2
5.Centering: m2/ m2
Grade beam= 0.35 < 0.40 < 0.45 m2 / m2
Slab, beam etc
Span | Single bay | Two bay |
4.0 m | 1.57 | 1.49 |
5.0 m | 1.51 | 1.45 |
6.0 m | 1.47 | 1.42 |
- RCC for isolated footing
RCC / m2 = X for LL
Total quantity = X A0 where A0 = Cumulative ultimate floor area in m2
SBC in KN/m2 | 3.0 KN/m2 | 5.0 KN/m2 | ||
Single bay | Two bay | Single bay | Two bay | |
50 | 0.216 | 0.188 | 0.245 | 0.215 |
75 | 0.137 | 0.119 | 0.155 | 0.137 |
100 | 0.089 | 0.077 | 0.100 | 0.088 |
120 | 0.071 | 0.062 | 0.080 | 0.071 |
150 | 0.055 | 0.048 | 0.062 | 0.055 |
200 | 0.041 | 0.036 | 0.046 | 0.041 |
220 | 0.035 | 0.0305 | 0.040 | 0.0354 |
250 | 0.030 | 0.026 | 0.0335 | 0.030 |
300 | 0.026 | 0.023 | 0.029 | 0.026 |
400 | 0.016 | 0.014 | 0.0185 | 0.0165 |
- RCC for grade beam:
Quantity / m2 = y
Single bay = 0.05
Two bay = 0.04
Total requirement = y Ag where Ag = area of G.F.
|
- RCC for superstructure:
RCC quantity = z for LL
RCC/Floor = z Af where Af = Area of floor in m2
Description |
Quantity = z for LL |
|||
3.0 KN/m2 | 5.0 KN/m2 | |||
Single bay | Two bay | Single bay | Two bay | |
RCC floor | 0.21 m3 / m2 | 0.19 m3 / m2 | 0.22 m3 per m2 | 0.20 m3 per m2 |
Note:
- This is inclusive of staircase and discontinuous sunshade but exclusive
of items (2) below.
- Include the following, if present:
- For slab thickness > 100 mm add extra quantity per m2 over 0.1m3
- For floor systems with primary and secondary beams add + 0.02 m3 / m2
- For canopy in G.F, add 01 m3 / m2
- For drops up to 1.20 m, add 01 m3 / m2
- For Continuous sunshade of 0.60 to 0.75 m alround the building, add 0.15 m3 / m2
- For sun- breakers up to 0.6 m, add 0.01 m3 / m2
Steel for slab, beam & column (item wise)
Description |
Live load 3 KN/m2 |
5 KN/m2 |
||
Single bay | Two bay | Single bay | Two bay | |
i. Slab | 0.100 | 0.100 | 0.10 | 0.10 |
ii. Beams | 0.065 | 0.055 | 0.07 | 0.06 |
iii. Columns | 0.045 | 0.035 | 0.05 | 0.04 |
iv. Staircase,sunshade etc. | 0.010 | 0.010 | 0.01 | 0.01 |
a. Qty / m3 with primary beams | ||||
b. Qty with primary and secondary beams | ||||
Steel required for columns reinforcement / m3 | ||||
with primary beam | ||||
400 | 45 | 38 | 48 | 42 |
300 | 41 | 35 | 43 | 38 |
225 | 37 | 32 | 39 | 35 |
with secondary beam | ||||
400 | 50 | 43 | 53 | 47 |
300 | 46 | 40 | 48 | 43 |
200 | 42 | 37 | 44 | 40 |
- Plastering in CM 1:5 – 12 mm thick:
2.3 to 2.6 m2 / m2 of plinth area
- Finishing the RCC::
2.4 m2 / m2 (10mm thick)
- White washing:
4.7 to 5.0 m2 / m2
- Wood scantling:
Doors D = 0.018 m3 / m2 of shutter area
Windows W = 0.019 m3 to 0.025 / m2 of shutter area
Ventilators V = 0.02 m3 / m2 of shutter area
Based on thumb rule
Wood required for door = 1 {Door area in m2 }
10 2
Wood required for glazed
window with ventilator = 1 {window area in m2}
12 2
Steel requirement / m2 on Plinth area basis
S.No. | Type of Building | Load bearing | Framed structure |
1
|
Residential Buildings | 25 to 30 Kg | 35 to 40 Kg |
2
|
Public Buildings | 30 to 35 Kg | 40 to 50 Kg |
Foundation & Basement Framed Structure (GF+ 3 Floors)
S.No. | Type of Building | Steel Qty. in Kg / m2 |
1
|
Residential Flats
(Multi storey ) |
5 Kg / m2 |
2 | Office Building
(a) Load Bearing (b) Framed |
4 Kg / m2 6..5 Kg / m2
|
3
|
Commercial Buildings such as Bus Stand, Restaurants etc.
|
7.5 Kg / m2 |
Approximate Quantity of steel requirement (General)
S.No. | Description | Qty. of Steel in Kg / m3 |
1 | Footings | 50 to 65 |
2 | Cast in situ Piles | 30 to 50
|
3 | Plinth Beam |
70 to 100
|
4 | Lintel | 100 to 130
|
5 | Column | 100 to 200
|
6 | Beam | 150 to 200
|
7 | Slab | 60 to 75
|
8 | Stairs | 90 to 120
|
Estimation of Quantity of Reinforcement
For rough calculation of reinforcement steel in construction Projects following thumb rule may be adopted:
(i) Slab 80 Kg / m3
(ii) Beam 110 Kg / m3
(iii) Column 160 Kg / m3
(iv) Footing slab 80 Kg / m3
MATERIAL REQUIRED ON PLINTH AREA BASIS FOR SINGLE STOREY LOAD BEARING RESIDENTIAL BUILDING
Component | Material required |
Brick | 500 Nos. /m2 |
Cement | 1.5 Bags /m2 |
Steel bars | 12 kg/m2 (MS bars)
8 kg/m2 ( Tor steel) |
requirement / m2 on Plinth area basis
S.No. | Type of Building | Load bearing | Framed Structure |
1 | Residential buildings | 5 to 6 Bags | 5 to 7 Bags |
2 | Public buildings | 4 to 5 Bags | 6 to 8 Bags |
3 | Residential Flats ( Multi storey) | —- | 3.2 to 4.0 Bags |
4 | Office building | 2.4 to 3.0 Bags | 5 Bags |
5 | Commercial buildings such as Bus Stand, Restaurants etc. | —– | 4.5 Bags |
For Foundation & Basement of Framed Structure (up to 4 Storeyed ) alone
S.No. | Type of Building | Load bearing | Framed Structure |
1 | Residential Flats | —- | 0.4 Bags / m2 |
2 | Office building | 0.36 Bags / m2 | 0.5 Bags / m2 |
3 | Commercial building | —- | 0.45 Bags / m2 |
Minimum Cement content required for various Grade of Concrete
S.No. | Grade of Concrete | Cement content in Kg / m3 of concrete | Max. W/c ratio | |
As per TCE (old code) | As per
IS 456 |
|||
1 | M15 | 285 | — | |
2
(i) |
M20
M20 (below G.L) M20 (above G.L) |
360 315 |
300 | 0.55 |
3
(i) |
M25
M25 (for Piles) M25 (for other structures) |
400 365 |
300
|
0.50 |
4 | M30 | 415 | 320 | 0.45 |
5
(i) (ii) |
M35
M35 (for Piles) M35 (for other structures) |
525 475 |
340 | 0.45 |
6 | M40 | 535 | 360 | 0.40 |
Note:-
As per IS 456 – 2000 Maximum cement content should not exceed 450 Kg / m3 for the cement mortar to ensure that heat of hydration and shrinkage cracking are prevented.
COST OF BUILDING (GENERAL)
- Cost of foundation & Plinth 18%
(Up to G.L. 13%
From G.L. to Plinth & DPC 5%)
- Cost of Brick work from Plinth to Roof 23%
- Cost of RCC works except roofing 6%
- Cost of flooring 20%
( RCC roof 15%
Lime terracing 5%)
- Cost of Flooring 6%
- Cost of Doors & Windows 20%
- Cost of Plastering & finishing 7%
Note: The cost excludes Water supply, Sanitary & Electrification.
COST OF MATERIALS & LABOUR FOR BUILDING WORK
Materials | % | Labour | % |
Brick | 16 | Mason | 8 |
Sand | 4 | Carpenter | 3.5 |
C.A. | 4.5 | Mazdoor | 12 |
Cement | 19 | ||
Timber in scantling | 9.5 | ||
Steel | 23.5 | ||
Total | 76.5 | 23.5 |
Overall 100%
SINGLE STOREY COST
Component | % |
Plinth | 18 |
Superstructure | 27 |
Flooring | 8 |
Roofing (Flat) | 20 |
Wood work | 17 |
Miscellaneous | 10 |
Total | 100 |
ORDINARY BUILDINGS
Materials | % | Labour | % |
Cement | 13 | Excavation | 1 |
Steel | 10 | Masons | 25 |
Timber | 12 | Carpenter | 12 |
Other Materials | 25 | Black smith | 2 |
Total | 60 | Total | 40 |